WELCOME to the Americano Beach Resort Hurricane Irma Update Center.  The Association will post updates and information here as they become available.  It remains the goal of the Americano Beach Resort Lodge Condominium Association to reopen the resort as soon as it is safe and prudent to do so.

To start receiving email updates, newsletters, and billing info please visit: www.arcpaperless.com to sign up!


Last updated: Thursday, March 28, 2019 (Find previous posts here.)

The contractors and team this month have started cleaning out the interior of the building. Progress is moving along and updated photos are posted above. We are continuing to pursue financing and are preparing a mailing for all owners. We have inspected and tested the PTAC units currently in the building and have cleaned and stored the ones that have passed all tests. All patio sliding glass doors are within a week or so of being completed. If you have any questions, please give us a call at (321) 320-8830 ext 1053.


January 10, 2019

The Americano Association would like to provide the following update:

The work on the tower exterior, including the windows, sealing and painting, are moving along and projected to be completed by the end of February. Although initial plans and specifications for the design and refurbishment of the unit interiors, common areas, and mechanical systems have been completed, the plans will not be finalized and submitted for required regulatory approvals until financing for the project has been secured. According to the developer, the developer continues to work with several interested and qualified parties on the required financing and expects to make an announcement soon. The Association, through the law firm of Berger Singerman, continues to pursue remaining insurance payments on both hurricane Matthew and Irma, and the Association continues to work with the Small Business Administration to secure a FEMA disaster repair loan. Unfortunately, that process is currently stalled due to the government shutdown.

The Association is planning a Special Meeting of the Owners to be held in February or March for the purpose of ratifying the amendments to the declaration required to complete the project's redevelopment. The proposed document changes will be mailed to all active owners in advance of the meeting, along with the meeting notice with meeting time and location.

Just a reminder from your Association, 2019 maintenance fees are late if not paid by January 15.


September 28, 2018

As of September 28, GC Contractors have started on the concrete repairs on the northside of the building. They have completed the removal of windows on the northside and continue to remove all windows from the southside of the building. US Glass continues to manufacture frames and prepare for the installation of the windows. Electrical sub-contractors continue the project of upgrading the power lines for the new PTAC (in-room air conditioners). The developer retained property, where the offices and sales center are located, began inviting owners to attend presentations on August 4th of what options are available to them if they have not yet paid the special assessments.​​​
----------------------------------------------------------------------------------------------------------------------------------------------

Check out the new drone footage of the work in progress at the Americano!

NEW! Updated March 2019